Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
Last revisionBoth sides next revision
student:scrumj:practices [2021/03/18 14:13] bernstdhstudent:scrumj:practices [2022/04/07 11:28] bernstdh
Line 26: Line 26:
 1. Click on the [[ https://docs.google.com/spreadsheets/d/1bI35ElgIrMCnwfhddW3lgvfDJKuZNDEJL4yiaKWd6ig/copy | scrumj link ]] to create a copy of a blank document. 1. Click on the [[ https://docs.google.com/spreadsheets/d/1bI35ElgIrMCnwfhddW3lgvfDJKuZNDEJL4yiaKWd6ig/copy | scrumj link ]] to create a copy of a blank document.
  
-2. Rename the copy to "Sprint1_TeamXX" where XX is replaced by your team number. (Note: It is a good idea to avoid the use of spaces in identifiers of all kinds since they are often used as delimiters.)+2. Rename the copy to something appropriate or to the name you were told to use. (Note: It is a good idea to avoid the use of spaces in identifiers of all kinds since they are often used as delimiters.)
  
-3. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>.+3. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>(Note: The start date should be the date the sprint actually starts, not the date of the planning meeting.)
  
 4. Add **all** of the team members to the "Assignments" page using just the ''local-part'' (i.e., the part before the ''@'' sign) of each member's email address (at JMU, this is the person's eid). NOTE: You cannot add team members after a story has been added. So, you must add all team members now. 4. Add **all** of the team members to the "Assignments" page using just the ''local-part'' (i.e., the part before the ''@'' sign) of each member's email address (at JMU, this is the person's eid). NOTE: You cannot add team members after a story has been added. So, you must add all team members now.
Line 75: Line 75:
 3. Click on <key>Scrum</key>+<key>Delete completed stories</key>. 3. Click on <key>Scrum</key>+<key>Delete completed stories</key>.
  
-4. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>.+4. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>(Note: The start date should be the date the sprint actually starts, not the date of the planning meeting.)
  
 5. Share the copy with all other team members using their eid@dukes.jmu.edu account and with the product owner using her/his eid@jmu.edu account. 5. Share the copy with all other team members using their eid@dukes.jmu.edu account and with the product owner using her/his eid@jmu.edu account.