Line 26: Line 26:
 1. Click on the [[ https://docs.google.com/spreadsheets/d/1bI35ElgIrMCnwfhddW3lgvfDJKuZNDEJL4yiaKWd6ig/copy | scrumj link ]] to create a copy of a blank document. 1. Click on the [[ https://docs.google.com/spreadsheets/d/1bI35ElgIrMCnwfhddW3lgvfDJKuZNDEJL4yiaKWd6ig/copy | scrumj link ]] to create a copy of a blank document.
  
-2. Rename the copy to "Sprint1". (Note: It is a good idea to avoid the use of spaces in identifiers of all kinds since they are often used as delimiters.)+2. Rename the copy to something appropriate or to the name you were told to use. (Note: It is a good idea to avoid the use of spaces in identifiers of all kinds since they are often used as delimiters.)
  
-3. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>.+3. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>(Note: The start date should be the date the sprint actually starts, not the date of the planning meeting.)
  
-4. Add the team members to the "Assignments" page using just the ''local-part'' (i.e., the part before the ''@'' sign) of each member's email address (at JMU, this is the person's eid).+4. Add **all** of the team members to the "Assignments" page using just the ''local-part'' (i.e., the part before the ''@'' sign) of each member's email address (at JMU, this is the person's eid). NOTE: You cannot add team members after a story has been added. So, you must add all team members now.
  
-5. Share the copy with all other team members and the product owner using their eid@dukes.jmu.edu account.+5. Share the copy with all other team members using their eid@dukes.jmu.edu account and with the product owner using her/his eid@jmu.edu account.
  
 After the planning meeting begins, one team member should then: After the planning meeting begins, one team member should then:
Line 71: Line 71:
 1. Copy the document containing the backlog for Sprint N-1. 1. Copy the document containing the backlog for Sprint N-1.
  
-2. Rename the copy to "SprintN" (with N replaced by the appropriate number).+2. Rename the copy to "SprintN_TeamXX" (with N replaced by the appropriate number and XX replaced by your team number).
  
 3. Click on <key>Scrum</key>+<key>Delete completed stories</key>. 3. Click on <key>Scrum</key>+<key>Delete completed stories</key>.
  
-4. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>.+4. Set the start/end dates by clicking on <key>scrumj</key>+<key>Set dates...</key>(Note: The start date should be the date the sprint actually starts, not the date of the planning meeting.)
  
-5. Share the copy with all other team members and the product owner using their eid@dukes.jmu.edu account.+5. Share the copy with all other team members using their eid@dukes.jmu.edu account and with the product owner using her/his eid@jmu.edu account.
  
 6.-14. Use the process for Sprint 1 6.-14. Use the process for Sprint 1